Applied Digital (NASDAQ: APLD), a U.S. based designer, developer, owner and operator of large-scale, purpose-built data centers engineered to support high-performance computing ("HPC") workloads, including artificial intelligence ("AI"), machine learning, and other accelerated-compute applications, today announced it has achieved Ready for Service for the second phase of Building 2 at its Polaris Forge 1 campus, delivering an additional 75 MW of critical IT load across three 25 MW data halls.

The milestone completes Building 2’s full 150 MW of critical IT load and brings fully operational critical IT load at Polaris Forge 1 to 250 MW. The fully leased AI Factory Campus is contracted to deliver 400 MW of critical IT load at full buildout.